Context
Polls in 2026 put local opposition to AI data centers between 46% and 75%; Gallup found 71% (March 2026). Opposition crosses party lines.
Stack layers
Contested layers: 1 Physical and energy foundations
Adjacent layers: 2 Compute, cloud and security
Contest dimensions
Power · Land · Water · Ratepayer costs · Local consent
Supporting competitive moves (this period)
Sep 16, 2026 · Compete · U.S. House / data center developers
Passed the Ratepayer Protection Act 417–3; awaits Senate
Primary source · www.naco.org
Oct 6, 2026 · Compete · San Francisco / data center developers
Urgency ordinance establishing a 45-day citywide data center moratorium
Primary source · missionlocal.org
Ecosystem Moves
How the players are building, buying and partnering to compete in this battleground. Newest first.
0 Build · 4 Buy · 9 Partner · 5 Compete
GE Vernova / Trench Group: $9B acquisition of a high-voltage transformer and bushing maker.
Move type: Buy · Oct 2026
NextEra / U.S. Commerce Department: Three gas hubs totaling 16.5 GW.
Move type: Partner · Oct 2026
Venture Global / GE Vernova: Frame agreements for up to 16 power islands for up to 10 GW of behind-the-meter AI compute.
Move type: Partner · Oct 2026
San Francisco / data center developers: urgency ordinance establishing a 45-day citywide data center moratorium
Move type: Compete · Oct 2026
Google / Constellation: 890 MW of new nuclear plus ~2.7 GW of supply.
Move type: Partner · Oct 2026
Amazon / Constellation: 20-year 690 MW Calvert Cliffs PPA.
Move type: Partner · Sep 2026
Eaton / COL Group: Medium-voltage capacity for data centers in EMEA.
Move type: Buy · Sep 2026
U.S. House / data center developers: passed the Ratepayer Protection Act 417–3; awaits Senate
Move type: Compete · Sep 2026
Vertiv / UtilityInnovation Group: On-site power for AI data centers; closed Oct 27.
Move type: Buy · Sep 2026
New York: Governor Hochul's Executive Order No. 62 imposed the first statewide data center moratorium, pausing state environmental permits for data centers of 50 MW or more until a generic environmental review is complete.
Move type: Compete · Jul 2026
Local opposition / projects: 75 major projects worth more than $130 billion delayed or canceled in Q1 2026, partly due to organized local opposition
Move type: Compete · Jun 2026
Nebius / Bloom Energy: fuel cells to power AI factory build-out; "Power remains a key constraint"
Move type: Partner · May 2026
Oracle / Bloom Energy: up to 2.8 GW of on-site fuel-cell power, 1.2 GW contracted
Move type: Partner · Apr 2026
Eaton / Boyd Thermal: completed $9.5 billion acquisition of the liquid-cooling maker
Move type: Buy · Mar 2026
White House / data center developers: Ratepayer Protection Pledge; developers commit to cover the full cost of new generation for their demand
Move type: Partner · Mar 2026
Constellation / CyrusOne: 380 MW for a new data center at the Freestone Energy Center, Texas; over 1.1 GW contracted in total
Move type: Partner · Feb 2026
Meta / Vistra / TerraPower / Oklo: nuclear agreements of up to 6.6 gigawatts for AI data centers
Move type: Partner · Jan 2026
Federal / states: the administration's AI preemption order leaves data center zoning to the states
Move type: Compete · Dec 2025